MANAJEMEN KONSTRUKSI PADA PELAKSANAAN LANJUTAN GEDUNG STADION INDOOR KABUPATEN LANDAK KALIMANTAN BARAT
Abstract
Construction management consultant is the management of construction project management with
large-scale projects. Analysis of the implementation of construction management can be applied to project
implementation to manage, organize, and find solutions, including the timing of the project implementation.
Good timing and management is one of the success factors of a construction construction project, managing
project management and implementing construction management in large-scale projects. Setting and managing
time with the aim of minimizing and reducing risks that may occur in an Indoor Stadium building project in
Landak Regency. The time risk that may occur is the delay in project completion.
Precise, fast, and safe timing are very helpful in completing the work on the Indoor Stadium building
construction project in Landak Regency. Good time management is the process of planning, organizing, and
controlling project execution. So that the timeliness at each stage of the work must be in accordance with the
planned time. Determination, management, and planning. Meanwhile, the extension of time is based on things
that have been coordinated with all parties and can be accounted for.
The purpose of this final project is to identify the various factors involved in the presence of a
construction management consultant at each stage of the project. This requires proper time management at
each stage of the work, so that the work is completed as expected. The implementation of this Final Project
includes: literature review, determination of required data, secondary data, and data analysis as well as
conclusions drawn from the analysis of the application of time management in construction projects and this
Final Project is carried out at the Indoor Stadium in Landak Regency.
Keywords: Cost Management, Human Resource Management, Time Management, Quality Management, Work
Safety Management
References
[1] A. soedrajat Sastraatmaja, (1984), Analisa
Anggaran Biaya Pelaksanaan, Penerbit Nova,
Bandung
[2] A Widiasanti, Irika dan Lenggogeni. (2013).
Manajemen konstruksi. Bandung: PT Remaja
Rosdakarya
[3] Bachtiar Ibrahim, (2001), Rencana dan
Estimate Real Of Cost, penerbit Bumi Aksara,
Jakarta
1 3
A.
1 LSM
B.
I PEKERJAAN STRUKTUR LANTAI, KOLOM DAN BALOK
A LANTAI I
Pekerjaan Lantai
M3
M3
KG
Sloof 10/15
M3
KG
M2
Tangga Naik (A) Dua Unit
M3
KG
M2
M2
M'
Tangga Darurat (B)
M3
KG
M2
M2
M'
SATUAN
LSM
LSM
DISETUJUI
PENGAWAS
Pembersihan Lokasi
Direksi Keet
Pembersihan menggunakan alat seperti parang, cangkul,
gergaji mesin dan lain-lain
NO URAIAN PEKERJAAN SPESIFIKASI
2 3 - - - -
Pembesian menggunakan besi Ø12
Bekisting papan mal kelas III, paku 5-10 cm dan cerucuk
Keramik Tangga Anti Slip 30 x 30 cm Keramik 30 x 30 cm unpolished (ex indogres)
Handle Tangga Stainless Steel Handle Tangga Stainless Steel
Pembesian menggunakan besi Ø12
Bekisting papan mal kelas III, paku 5-10 cm dan cerucuk
Keramik Tangga Anti Slip 30 x 30 cm Keramik 30 x 30 cm unpolished (ex indogres)
Handle Tangga Stainless Steel Handle Tangga Stainless Steel
Beton mutu beton menggunakan k 250
Pembesian pembesian menggunakan besi wiremesh m6
Beton mutu beton menggunakan k 250
pembesian menggunakan besi Ø12
bekisting papan mal kelas III, paku 5-10 cm dan cerucuk
Beton mutu beton menggunakan k 250
2 4
PEKERJAAN PENDAHULUAN
Papan Nama Proyek papan mal kelas III, paku 5-10 cm dan cerucuk
PEKERJAAN STRUKTUR
Urugan Pasir Lantai Pasir urug
Beton mutu beton menggunakan k 250
(a) (b) (c) (d)
sengatan binatang berbisa
Terkena Benda Tajam
Tertimpa potongan kayu
Terkena Benda Tajam
Terkena serpihan kayu
Terpeleset saat membawa adukan beton
Iritasi kulit akibat dari semen
terkena benda tajam
Terpeleset saat membawa adukan beton
Iritasi kulit akibat dari semen
terkena benda tajam
Terjatuh dari ketinggian
Terpeleset saat membawa adukan beton
Iritasi kulit akibat dari semen
terkena benda tajam
Terjatuh dari ketinggian
Terpeleset saat membawa adukan beton
Iritasi kulit akibat dari semen
terkena benda tajam
Terjatuh dari ketinggian
Terpeleset saat membawa adukan beton
Iritasi kulit akibat dari semen
terkena benda tajam
Terpeleset saat membawa adukan beton
Iritasi kulit akibat dari semen
terkena benda tajam
Tertimpa benda dari atas
Terpeleset saat membawa adukan beton
Iritasi kulit akibat dari semen
terkena benda tajam
Tertimpa benda dari atas
Terpeleset saat membawa adukan beton
Iritasi kulit akibat dari semen
terkena benda tajam
Tertimpa benda dari atas
10
PEKERJAAN
FINISHING LANTAI,
DINDING DAN
PLAFOND Lt 3
Body hernes , s epa tu,
helm, s arung ta nga n, dan
rompi s efety
Body hernes , s epa tu,
helm, s arung ta nga n, dan
rompi s efety
8
PEKERJAAN
FINISHING LANTAI,
DINDING DAN
PLAFOND Lt 1
Body hernes , s epa tu,
helm, s arung ta nga n, dan
rompi s efety
PEKERJAAN
FINISHING LANTAI,
DINDING DAN
PLAFOND Lt 2
6 9
Pekerjaan plat Lt. 3
Body hernes , s epa tu,
helm, s arung ta nga n, dan
rompi s efety
7
Pekerjaan pembuatan
tangga
Body hernes , s epa tu,
helm, s arung ta nga n, dan
rompi s efety
Body hernes , s epa tu,
helm, s arung ta nga n, dan
rompi s efety
5 Pekerjaan plat Lt. 2
3 Pekerjaan Sloof Lt. 1 sepatu, helm, s arung
ta nga n, dan rompi sefety
sepatu, helm, s arung
4 Pekerjaan plat Lt. 1 ta nga n, dan rompi sefety
sepatu, helm, s arung
2 Pembuatan Direksiket ta nga n, dan rompi sefety
no Pekerjaan/Kegiatan Identifikasi Bahaya Alat Pelindung Diri
yang diperlukan
1 Pembersihan Lokasi Sepatu, Helm, s arung
Tangan, dan Rompi Sefety
1 Sepatu 40
2 Helm 40
3 Rompi Sefety 40
4 Sarung Tangan 40
5 Body Hernes 20
6 Masker 40
7 Kaca Mata Las 2
Nama APD Yang
NO Diperlukan Jumlah APD Yang Diperlukan (satuan Buah)
8
[4] L Putri, dan syafriandi. 2014. Manajemen
konstruksi dengan Aplikasi mikrosoft Project.
Yogyakarta: Penerbit Andi
[5] PMPU (2014) Peraturan Mentri Pekerjaan
Umum Nomor 05/PRT/M/2014. Tentang
Pedoman Sistem Manajemen keselamatam
dan kesehatan Kerja (SMK3) Kontruksi
Bidang Pekerjaan Umum.
[6] Sagala, S. 2001. Manajemen Strategi dalam
Peningkatan Mutu Pendidikan, Bandung: CV.
Alfabeta.
[7] Samsudin, S. 2006. Manajemen Sumber
Daya Manusia. Bandung: Pustaka Setia.
[8] SNI ISO 9001 (2015) International
Organization for Standardization. Sistem
Manajemen Mutu-persyaratan.
[9] Soeharto, Iman, (1997). Manajemen Proyek:
Dari Konseptual sampai Operasional. Editor
Yati Sumiharti, cet. 3. Jakarta: Erlangga.